I have a question for you, as it is in the title. But maybe some prelude first.
Few days ago, I've talked with my friend about his project. He told me, that because of Xmas and some team members holidays, they decided to suspend next sprint start for new year. They have 2 weeks sprints. He also told me, that other way they can have 3 days spirnt (according to Xmas). They want to have full time sprint, so they'll start in the new year.
I told, that in my opinion they should start 3 days sprint, and plan less tasks.
Who had rigth in this case ?