Hi all,
I am going to make my second test for PSM I, since I failed first time (81%).
(The open test did not help me in this case, since I finished 10 times with 100%)
Due to the fact, that English is not my mother tongue, I have had some difficulties to understand the detailed meaning of some questions and there answers here in the forum.
Even if I had have my question in some threads, I like to put my questions in one thread, to keep it in one place.
So here we go with the unclear topics of my Scrum knowledge:
1. Team has a conflict member, who s going to remove that member
A1. the scrum master, because of removing impediments
A2. the self-organized team (development team)
A3. xxxxxxxx
If I read the forum, I have A1 and A2 as valid answers. But sometimes (within my classes) it was stated it should be only A2.
2. Which of these should be delivered at the end of a sprint (choose 2)
A1. increment with minor bugs (since they could be of earlier increments)
A2. single document, as requested by the PO
A3. increment of working software that is done
I am certain on A3, but the document issue and the bugs have been under discussion.
Some advise would be nice
3. what describes sprint planning topics best
A1. What can be done and how to do it
A2. How conditions have changed and how the PB should evolve
A3. What went wrong and what to do different
A4. Who is on the team and what team member roles will be
Her I go for A1 and A2, since the rest is not in the Sprint planning
4. What is reasonable to go for a four-week sprint instead of a two-weeks sprint
A1. The organizations release cadence is 4 weeks
A2. The DT cannot commit for two-week-sprints, but monthly sprints
A3. The PO cannot articulate the sprint goal and the incremental value fits only in a for weeks sprint
I go for A1 and A2.
5. What happens if the time box (sprint) expires and we have thing left.
A1. the PBI which are done, could be potential released
A2. the remaining PBIs going back to the PB and will be refined
A3. xxxxxxxxx
A1 and A2 are great for me
Thanks to all for the effort to give me a hand on these questions.
Best for now
Frank
I am going to make my second test for PSM I, since I failed first time (81%).
(The open test did not help me in this case, since I finished 10 times with 100%)
Due to the fact, that English is not my mother tongue, I have had some difficulties to understand the detailed meaning of some questions and there answers here in the forum.
Even if I had have my question in some threads, I like to put my questions in one thread, to keep it in one place.
So here we go with the unclear topics of my Scrum knowledge:
1. Team has a conflict member, who s going to remove that member
A1. the scrum master, because of removing impediments
A2. the self-organized team (development team)
A3. xxxxxxxx
If I read the forum, I have A1 and A2 as valid answers. But sometimes (within my classes) it was stated it should be only A2.
2. Which of these should be delivered at the end of a sprint (choose 2)
A1. increment with minor bugs (since they could be of earlier increments)
A2. single document, as requested by the PO
A3. increment of working software that is done
I am certain on A3, but the document issue and the bugs have been under discussion.
Some advise would be nice
3. what describes sprint planning topics best
A1. What can be done and how to do it
A2. How conditions have changed and how the PB should evolve
A3. What went wrong and what to do different
A4. Who is on the team and what team member roles will be
Her I go for A1 and A2, since the rest is not in the Sprint planning
4. What is reasonable to go for a four-week sprint instead of a two-weeks sprint
A1. The organizations release cadence is 4 weeks
A2. The DT cannot commit for two-week-sprints, but monthly sprints
A3. The PO cannot articulate the sprint goal and the incremental value fits only in a for weeks sprint
I go for A1 and A2.
5. What happens if the time box (sprint) expires and we have thing left.
A1. the PBI which are done, could be potential released
A2. the remaining PBIs going back to the PB and will be refined
A3. xxxxxxxxx
A1 and A2 are great for me
Thanks to all for the effort to give me a hand on these questions.
Best for now
Frank