Dear all,
I am preparing for my PSM1 exam and desperatly trying to figure out why the answer "using a dedicated development team" to the following question is marked as wrong:
Which of the following are mandatory in Scrum?
options:
Measuring the performance of the Sprints
Using Sprint Backlogs
Using burn-down charts
Using pair-programming
Using test-driven development
Using a dedicated Development Team
The explanation is: