Sprint Retrospective and Product Owner

$
0
0

Question :

During a Sprint retrospective, for what is the Product Owner responsible for ?

a) Capturing requirements for the Product Backlog

b) The Product Owner should not take part in Sprint Retrospectives

c) Participating as a Scrum Team member

e) Summarizing and reporting the discussions to the stakeholders that he/she represents in the Scrum Team

 

It is optional that the Product Owner attends to this meeting in the Scrum Guide. So I'd answer c. Is it correct ?